Mechanics Lien Deadlines in Florida
In Florida, a claim of lien must be recorded within 90 days after final furnishing, lienors not in privity with the owner must serve a notice to owner within 45 days of starting, and suit must be filed within 1 year after recording.
Last checked . General information, not legal advice.
Florida at a glance
- Deadline to record lien
- 90 days after final furnishing
- If the original contract is terminated, a lien must be recorded within 90 days after termination or 90 days after final furnishing, whichever is first.
- Preliminary notice required
- Yes in some cases (notice to owner, non-privity lienors)
- Lienors not in privity with the owner (except laborers) must serve a notice to owner before or within 45 days after starting work.
- Deadline to enforce lien
- 1 year after recording
- The owner can shorten this by filing a notice of contest of lien.
The rules in Florida
How long does a contractor have to file a mechanics lien in Florida?
Deadline to record lien in Florida: 90 days after final furnishing. If the original contract is terminated, a lien must be recorded within 90 days after termination or 90 days after final furnishing, whichever is first.
Is a preliminary notice required before filing a mechanics lien in Florida?
Yes in some cases (notice to owner, non-privity lienors). Preliminary notice required in Florida: yes in some cases (notice to owner, non-privity lienors). Lienors not in privity with the owner (except laborers) must serve a notice to owner before or within 45 days after starting work.
How long do you have to foreclose a mechanics lien in Florida?
Deadline to enforce lien in Florida: 1 year after recording. The owner can shorten this by filing a notice of contest of lien.
Where do the Florida mechanics lien deadlines come from?
The rules above come from Fla. Stat. 713.08, Fla. Stat. 713.06, Fla. Stat. 713.22 and Fla. Stat. 713.132. Each source is linked on this page. We last checked them in October 2026.
Good to know
An owner can record a notice of termination that ends the notice of commencement 30 days after recording or on a later stated date (Fla. Stat. 713.132, last amended in 2023).
What this means in practice
Deadlines often differ by role. The period for a general contractor who dealt directly with the owner can be different from the period for a subcontractor or supplier, and residential projects can have their own rules. Check which category fits before relying on a single number.
The event that starts the clock matters as much as the length of the period. Depending on the statute, it can be the last day labor or materials were furnished, completion of the project, or the recording of a notice of completion or commencement by the owner. Keeping dated records of the last work performed helps establish the start date.
Recording a lien is not the end of the process. If the debt is not paid, the claimant generally has to file a lawsuit to foreclose the lien within the enforcement period, or the lien expires. When the debt is paid, the owner will usually want a signed lien release recorded so the title is clear.
General information, not legal advice. Laws change, and cities can add their own rules, so check the current statute before you rely on it.
Compare with neighboring states
Compare all statesMore Florida rules
- Adverse Possession Laws in Florida
- Transfer on Death Deed Laws in Florida
- Tenant Abandoned Property Laws in Florida
- Age of Majority and Emancipation in Florida
- Child Custody Preference Age in Florida
- When Child Support Ends in Florida
- Common Law Marriage in Florida
- Corporation Filing Fees in Florida
- Security Deposit Laws in Florida
- Eviction Notice Requirements in Florida
- Will Requirements in Florida
- All Florida documents and rules